Five Phases of Construction

The Maybank Highway Improvements Phase 2 Widening Project is divided into five (5) separate phases of construction. Various construction tasks are scheduled for completion during each phase. The project duration is 15 months. 

As of 8/23/2018: Installing the last layer of asphalt and then entering phase 5.

Notice to Proceed: June 12, 2017

Substantial Completion: September 11, 2018

 

Install construction signs

JUNE 2017 - July 2017

Install construction signs, erosion control, tree protection, clearing & grubbing.

 

August 2017 - April 2018

Construct outfall ditches, closed storm drainage, curb & gutter, and sidewalks.

 
03_3_orig.jpg

May 2018 - June 2018

Begin pavement buildup, asphalt pavement, install concrete medians.

 

July 2018

Install guardrail, permanent pavement markings and signs.

 

August 2018

Install new traffic signals and configuration of signal timings.

Substantial Completion Date: September 11, 2018